August 10, 2026
Last year, the US Army Corps of Engineers announced that the Grand Strand would be the recipient of a new round of beach renourishment in the winter of 2025-2026. This is a much-needed process that replaces beach sand lost to storms and other erosion and ensures that our area has a gorgeous, wide sandy beach for years to come.
The project was initially scheduled to begin in late fall 2025 and be completed in all three “reaches” (North Myrtle Beach, Myrtle Beach and Garden City Beach/Surfside) before Easter, but equipment malfunctions and weather delays led to a late start and slower-than-expected progress. By January, we were being told that the project would wrap up by the end of May, but problems and delays continued to plague the project. In May, the project was finishing up in North Myrtle Beach, and we were hopeful that the Corps would shut everything down for the summer and start again in the fall. Unfortunately, that wasn’t the case. The work proceeded in downtown Myrtle Beach throughout May and June, and as recently as July 1, we were told that it would not begin in our area until mid-July. However, on the morning of the Fourth of July, we woke up to find that the work had begun at 2:00 AM and at a location three miles from where we were told it would start.
The project consists of a large (3’ diameter) pipe called a “subline” that runs from a dredging ship stationed miles offshore to the beach, and then turns and runs up or down the shoreline from that landing location. Sand is pumped through that pipe to the beach, where it is smoothed and graded by bulldozers. The good news is that actual work moves very quickly, and it is rare that access to the beach in front of any property is closed for more than 24-36 hours. It’s true that for that time, it can be pretty disruptive; however, once the active work has passed, the only “reminder” will be a pipe on the beach over which the contractors will build sand ramps for ease of access. (We’ve also found that you’ll have some of the best seashell hunting in the world for those first few days!)
We are happy to say that all active work has been completed in Garden City Beach and Surfside Beach as of Tuesday, August 11. The only remaining sign of the project is the pipe running from 5th Avenue N in Surfside Beach to the northern town limit, but with work coming to a close at the Myrtle Beach State Park yesterday, we expect it to begin being dismantled and removed at any time. This work has been done at night in all other areas, and we’d expect the same here.
Garden City Beach:
1) “The Point” to 1087 S. Waccamaw Dr.: No work to be done, and the beach is fully open.
2) 1087 S. Waccamaw Dr. to the Garden City Pier: Work is complete and the beach is fully open.
3) Garden City Pier to Melody Lane: Work is complete and the beach is fully open.
Surfside Beach
1) Melody Lane to 5th Avenue North: Work complete and/or not being performed, and the beach is fully open.
2) 5th Avenue North to 12th Avenue North: This area has not been renourished, but pipe has been run to service ongoing work to the north. The beach is fully open with sand ramps over the pipe, and the pipe itself should be removed within the next few days.
3) 12th Avenue North to 17th Avenue North: Work is complete and the beach is fully open with sand ramps over the pipe, and the pipe should be removed within the next few days.
We have been continually frustrated by the fact that the dredging company has decided to use the schedules they publish as mere guidelines, and that’s made it difficult to know which properties will be affected at any time. Rest assured that we will be compensating you for any period of time that the beach is closed in front of your property, and that other amenities (pools, etc.) will remain open. We are thankful for your patience, and please know that this project will lead to a wider and more beautiful beach for years to come!